Construction Update (May)
Kitchen equipment – commercial dishwasher ready for installation
Audio-Visual System – alternate video wall system scheduled for installation on May 9th
East entry rain chain – complete and installed
Fire suppression system – pump repair complete and scheduled for installation May 2nd
Concession stand – cabinets/countertops in place and ready for equipment installation
Hendrickson Road entrance – all base walls compete, finish work commencing, color sign in place
Gift shop and exhibit room glass doors – pending bid from new glass contractor
Park Host fencing – construction along east property line continues
Building/Parking Lot Landscaping – plants on site, installation scheduled to begin May 9th
East Entrance Bridge Railing – designed and under fabrication
Asphalt Paving – scheduled late May/early June once entrance structure is complete
Rain chain: Kirk Nelson, who designed and fabricated the copper mail rain chain at the east entrance
Fence: East fence line at Park Host site – nearly complete!